Archive > Construction Projects > J D'Amico Inc., Section 28 Suction to Brattle Court Pump StationSection 28 Suction to Brattle Court Pump Station: MWRA Contract # 6546 |
|||||||||||||||||||
![]() |
![]() |
![]() |
D'Amico Installing 54" Flanged Butterfly Valve |
||||||||||||||||
![]() |
![]() |
||||||||||||||||||
![]() |
![]() |
||||||||||||||||||
![]() |
![]() |
||||||||||||||||||
![]() |
![]() |
||||||||||||||||||
![]() |
|||||||||||||||||||
Phase 3 included the installation of a new 54" butterfly valve on MWRA's WASM 3 line |
|||||||||||||||||||
Contractor:
|
Materials Included: 54" Flanged Butterfly Valves and 20" Gate Valves With Blow-OffsSummary:The Section 28 Project to rehabilitate the Section 28 pipeline in Arlington was awarded to J D'Amico by MWRA. Section 28, constructed in 1899, is the oldest of the suction mains serving The Brattle Court Pump Station. The photos above are from Phase 3 which included the installation of a new 54" valve on WASM 3 line and new interconnections with Section 28.For more info contact Richie Ross, WWSC Outside Sales, Malden, MA at 781.844.4216 |
||||||||||||||||||